Olive Avenue Corridor
Program Overview
Olive Avenue is a significant thoroughfare for residents and travelers in the western part of Maricopa County. With its prominent roadway connections to SR Loop 303 and SR Loop 101, traffic projects for Olive Avenue in the west valley are expected to increase over the next 20 years. MCDOT is moving forward with several projects along Olive Avenue in this area to increase capacity, improve safety and make roadway operations more efficient.

Program Segments & Schedule
Description of Work |
Status |
This project will widen Olive Avenue from Citrus Road to just east of Cotton Lane from two lanes to four travel lanes with a striped median to increase capacity and improve safety. An existing railroad crossing on Olive Avenue will be removed and an existing railroad crossing on Cotton Lane will be improved. The project will also realign Olive Avenue to the south to tie into the Arizona Department of Transportation’s (ADOT) planned intersection with State Route Loop 303.
Project Budget
Phase |
FY 19 |
FY 20 |
FY 21 |
FY 22 |
FY 23 |
FY 2019 to 2023 Total |
Scoping |
— |
— |
— |
— |
— |
— |
Design |
2,000,000 |
500,000 |
— |
— |
— |
2,500,000 |
Construction |
11,422,000 |
1,004,000 |
— |
— |
— |
12,426,000 |
Project Total |
13,422,000> |
1,504,000> |
—> |
—> |
—> |
14,926,000> |
|
Construction: Summer 2018
|
Description of Work |
Status |
This project will widen Olive Avenue west of State Route 303 to just east of Sarival Avenue. The widened roadway will include four travel lanes with a center paved turn lane to better support regional traffic flow. The project will also install a traffic signal at the intersection of Sarival Avenue and with Olive Avenue. The intersection will be widened to provide for additional turn lanes to improve capacity at the intersection to meet future traffic demands.
Project Budget
Phase |
FY 19 |
FY 20 |
FY 21 |
FY 22 |
FY 23 |
FY 2019 to 2023 Total |
Scoping |
— |
— |
— |
— |
— |
— |
Design |
2,514,000 |
1,000,000 |
400,000 |
— |
— |
3,914,000 |
Construction |
1,370,000 |
8,880,000 |
— |
— |
— |
10,250,000 |
Project Total |
3,884,000> |
9,880,000> |
400,000> |
—> |
—> |
14,164,000> |
|
Construction: Spring 2019
|
Description of Work |
Status |
This project will widen Olive Avenue beginning east of Sarival Avenue to east of Reems Road. The widened roadway will include four travel lanes with a center paved turn lane to better support regional traffic flow. The project will also install a traffic signal at the intersection of Reems Road and with Olive Avenue. The intersection will be widened to provide for additional turn lanes to improve capacity at the intersection to meet future traffic demands.
Project Budget
Phase |
FY 19 |
FY 20 |
FY 21 |
FY 22 |
FY 23 |
FY 2019 to 2023 Total |
Scoping |
— |
— |
— |
— |
— |
— |
Design |
1,254,000 |
1,000,000 |
400,000 |
— |
— |
2,654,000 |
Construction |
— |
3,980,000 |
6,270,000 |
— |
— |
10,250,000 |
Project Total |
1,254,000> |
4,980,000> |
6,670,000> |
—> |
—> |
12,904,000> |
|
Construction: Winter 2020
|
Related Files
Questions? Contact the Program Team
Email Us
Project Information: 602-506-3342