Project Description

The goal of the project is to eliminate excessive water ponding on pavement surfaces and prevent standing water in driveways along 132nd Street. 

Construction is tentatively planned for January 2025. Schedule is subject to change for reasons beyond MCDOT’s control, including weather, equipment failure, illness or other circumstances.

For information about Title VI, please visit our information page.

Project Mini Map
Project Map (Aerial)

Project Info

Scoping Schedule: 2024

Design Schedule: 2024

Construction Schedule: January 2025

Project Phase

Current Phase: Design