Primrose Estates Phase 2 and Buckeye North Pavement Rehabilitation

Project #: TT0790

Project Description

The Maricopa County Department of Transportation (MCDOT) will be performing a roadway rehabilitation project on selected roadways in the Buckeye area to extend the life of the road and provide an improved driving surface for vehicles. Crews will be milling and replacing asphaltic concrete pavement along several sections in the Buckeye area. Work will begin on Tuesday, May 26, 2026 and continue through the end of July 2026.

During construction, lane restrictions will be in place along with a flagging operation, and it is advised to allow extra time for travel in the area. Access to properties will be maintained at all times during construction.


The project includes:

  • Milling/removing old asphaltic concrete pavement at select locations.
  • Installing new asphaltic concrete pavement overlay.
  • Cleaning up the work zone and other miscellaneous work.


Please watch for work crews, obey all traffic control signs and slow down in the work zone.


Work Schedule:

Where: Please see map for locations.

When: Tuesday, May 26, 2026 through late July 2026. Monday through Friday, 6 a.m. to 4 p.m.

No weekend or holiday work is anticipated.

For information about Title VI, please visit our information page.

Project Mini Map
Project Map (Aerial)

Project Info

Scoping Schedule: March 2026

Design Schedule: April 2026

Construction Schedule: Tuesday, May 26, 2026 through the end of July 2026

Project Phase

Current Phase: Construction