Fort McDowell Road and Mohave Road Intersection Improvements

Project #: TT0721

Project Description

This project is located within the Fort McDowell Yavapai Nation (FMYN) and is in response to a request from the FMYN to address traffic delays for vehicles entering Fort McDowell Road from Mohave Road. The objective is to design an intersection control that includes two-lane approaches (one left and one right) to Mohave Road from Fort McDowell Road. The intersection would be designed to design capacity anticipated to 2050.

The project will be constructed within the existing right-of-way with no change to roadway capacity or alignment.

For more information email [email protected] or call 602-506-3342.

Schedule is subject to change for reasons beyond MCDOT’s control, including weather, equipment failure, illness or other circumstances.

For information about Title VI, please visit our information page.

Project Mini Map
Project Map (Aerial)

Project Info

Scoping Schedule: November 2022 - March 2024

Design Schedule: April 2024 - October 2025

Construction Schedule: Spring 2026

Project Phase

Current Phase: Design