Fort McDowell Road and Mohave Road Intersection Improvements
Project #: TT0721
Project Description
This project is located within the Fort McDowell Yavapai Nation (FMYN) and is in response to a request from the FMYN to address traffic delays for vehicles entering Fort McDowell Road from Mohave Road. The objective is to design an intersection control that includes two-lane approaches (one left and one right) to Mohave Road from Fort McDowell Road. The intersection would be designed to design capacity anticipated to 2050.
The project will be constructed within the existing right-of-way with no change to roadway capacity or alignment.
For more information email [email protected] or call 602-506-3342.
Schedule is subject to change for reasons beyond MCDOT’s control, including weather, equipment failure, illness or other circumstances.
For information about Title VI, please visit our information page.
Project Info
Scoping Schedule: November 2022 - March 2024
Design Schedule: April 2024 - October 2025
Construction Schedule: Spring 2026
Project Phase
Current Phase: Design