Sun City West Units 35, 38A, 40 Roadway Rehab
Project #: TT0638
Project Description
Roadway segments in Sun City West, 5.5 miles total, are recommended by the Maricopa County Department of Transportation (MCDOT) Pavement Management Branch for pavement maintenance.
Regular pavement maintenance protects MCDOT's assets by maintaining structural integrity, improving rideability and safety, and ensuring longevity of the roadway.
The project includes:
- Removing the existing asphaltic concrete pavement, re-grading the existing aggregate base, and installing new asphaltic concrete pavement.
- Removing and constructing new roadway signage and pavement markings where needed.
Work Schedule:
- Where: Roadways located in the area of R.H. Johnson and Stardust boulevards.
- When: Monday, May 4, to November 2026.
- Hours: Monday - Friday, 6 a.m. to 6 p.m.
No weekend or holiday work is anticipated.
Click here for more project details and traffic alerts as they become available.
Schedule is subject to change for reasons beyond MCDOT’s control, including weather, equipment failure, illness or other circumstances.
For information about Title VI, please visit our information page.
Project Info
Scoping Schedule: 2021
Design Schedule: 2024
Construction Schedule: May 4 to November 2026
Project Phase
Current Phase: Construction