MC 85 at Verrado Way

Project #: TT0572

Project Description

A Traffic Signal Warrant Study completed by MCDOT indicated the need for a traffic signal at the intersection of MC 85 and Verrado Way. The goal of this project is to construct a signalized intersection to help improve roadway conditions at the intersection. Roadway improvements will extend approximately 1,500 feet north of the intersection and 1,200 feet south of the intersection.


For information about Title VI, please visit our information page.

Project Mini Map
Project Map (Aerial)

Project Info

Scoping Schedule: April 2017 - July 2018

Design Schedule: August 2018 - January 2024

Construction Schedule: February 2024 - July 2024

Project Phase

Current Phase: Construction