Sun Lakes Rehab Units 11-22

Project #: TT0623

Project Description

The Maricopa County Department of Transportation (MCDOT) will be doing a pavement rehabilitation project within the Sun Lakes, Units 11-22 community, beginning July 5, 2023 through November 2, 2023.

This work will be performed in 8 phases, with each phase expected to last 2 weeks. Pavement rehabilitation work includes removing the old roadway surface (milling) and replacing it with new asphalt (paving). The work may temporarily block access to driveways, but crews will be available to assist drivers as needed. Temporary "No Parking" signs will be posted 48 hours before work starts on your road. Please do not park on the road until the signs are removed. Please watch for restricted lanes as you travel through the area, obey traffic control signs and slow down in the work zone.

MCDOT is working with all its stakeholders. Coordination with the HOA, trash collection, postal delivery, and emergency services will continue throughout the duration of the project.

For additional project information, visit: www.maricopa.gov/5806/Sun-Lakes-Pavement-Rehabilitation

For information about Title VI, please visit our information page.

Project Mini Map
Project Map (Aerial)

Project Info

Scoping Schedule:

Design Schedule:

Construction Schedule: July 11, 2023 - November 2, 2023

Project Phase

Current Phase: Construction

Subscribe to our newsletter

Project Updates

Revised Project Schedule

Posted On: 8/7/2023

The Maricopa County Department of Transportation (MCDOT) is revising the construction schedule for the Sun Lakes Pavement Rehabilitation project. In addition, we will also be changing our construction approach by removing the entire width of the roadway pavement and replacing with new asphalt versus the half-lane construction we initially started with on Phase 1 & 2.

Revised Project Schedule:

  1. Phase 1 + 2 anticipated to be complete by the end of August
  2. Phase 3 anticipated to start by Late August
  3. Phase 4 anticipated to start in September
  4. Phase 5 anticipated to start in late Sept/early October
  5. Phase 6 anticipated to start in October
  6. Phase 7 anticipated to start in late October/early November.


It is important to know that during the construction of your road, residents will still be able to leave and enter their home as needed. Crew members will be available to assist drivers get in and out of their driveway if needed while they are working on your road. We ask that you please use caution when driving on the road.

Temporary "No Parking" signs will be posted 48 hours before work starts on your road. Please do not park on the road until the signs are removed.  Vehicles that have not been moved will be towed to the Sun Lakes Cottonwood Country Club parking lot, and the HOA will be contacted to assist with notifying the owner.

Coordination with the HOA, trash collection, postal delivery and emergency services will continue throughout the duration of the project.